CASPER, Wyo. — With work all but completed on the road reconstruction project spanning Poplar Street to David Street, the Casper City Council on Tuesday approved a $29,296 amendment due to delays.

With Casper roads crews on the third and final phase of the project — involving work from Walnut Street to Poplar Street — all utitlities, lighting, signage, ADA-compliant crosswalks and more have been completed. However, delays were caused by the need for additional inspection time.

After originally contracting with WWC Engineering for $281,456, the new total cost for the project sits at $310,752.

Oil City News LLC is a nonpartisan media organization and Central Wyoming’s largest locally owned, independent news platform. The mission of Oil City’s award-winning team of Casper-based journalists is to build a more informed and connected community by producing local stories first, fast and forever free. If you would like to read the original article, click here.